Prior to finalizing the bidding documents, input from all the stakeholders was got and duly incorporated in them.
The official said that the case for approval of the award of O&M outsourcing contract was sent to the GENCO-III BoD on October 29, 2014. The BoD (GENCO-III) principally endorsed the proposal of engaging O&M service provider and directed the Nandipur management to go ahead, negotiate and finalize the contract price as well as the terms and conditions with M/S TNB, Malaysia and then put up the case again to the BoD for final approval before signing the contract.
He said that when the case was again presented, after duly addressing the observations along with other agenda items, the GENCO-III BoD took an indifferent stance to the matters of Nandipur project by setting aside all the agenda items for getting approval from GENCO-V BoD instead of GENCO-III BoD.
However, due to intervention by the water and power minister in his meeting with joint BoDs of GENCO-III and GENCO-V, the GENCO-III BoD started considering the agenda but only after the cases recommended by the GENCO-V BoD. All the information or clarification regarding any matter has been provided by Nandipur management to GENCO-III.
The official said that after a lapse of seven months, the GENCO-III BoD scrapped the tender of O&M outsourcing and required prior approval from the Executive Committee of National Economic Council (ECNEC) for fresh case, in spite of the fact that O&M outsourcing of GENCOs is part of the National Power Policy 2013. The National Electric Power Regulatory Authority (Nepra) and the water and power ministry have also directed to outsource the O&M services of the Nandipur power plant.
The plant achieved its contractual Commercial Operation Date (CoD) on July 23, 2015 after successful Performance Tests and Reliability Test Run (RTR). Both the output and efficiency of the power plant have been found 4.68pc and 0.47pc respectively above the contractual guarantees.
However, after its successful testing and operation, the same was stopped on August 10, 2015, as there was no arrangement of O&M services because the EPC (engineering, procurement and construction) contractor was not obliged to operate further under the agreement.
The official said that the shutdown status of the power plant after its completion and RTR was not a new development and all the concerned knew very well owing to the non-award of the O&M outsourcing.
However, due to inadequacy and lack of capacity of the in-house staff and resources, there was no option left with the technical team of the Nandipur project but to keep the plant closed rather than handing it over to the inexperienced personnel.
The official said that in spite of successful completion of the project, the Taking Over Certificates (ToCs), STG (Steam Turbine-Generator) and that of BoP (Balance of Plant) have not been issued to the contractor to keep extra leverage in favour of the employer.
The Fuel Oil Treatment Plant (FOTP) was supplied by the EPC contractor for treatment of High Sulfur Furnace Oil (HSFO). The nameplate capacity of the plant was in accordance with the contract agreement. However, the actual performance of the FOTP can only be confirmed after testing and commissioning at site, with the supplied untreated HSFO, the official said.
After installation of the FOTP, the testing and commissioning work was started by the EPC contractor through M/S GEA Weastfalia in September 2014.
However, after repeated attempts, the optimum capacity of the FOTP could not be achieved. The employer and the engineer immediately took up the matter with the EPC contractor for its early resolution as per its agreement.
In the meantime, an inquiry was conducted by the water and power ministry to find out the issues, reasons and solution regarding the FOTP in May 2015. The Nandipur management had already taken up the matter with the EPC contractor for its resolution under intimation to all the concerned.
The actions of the GENCO-III and its BoD have made the O&M process controversial. The case for engaging EPC contractor for the O&M services as a time gap arrangement was submitted in June 2015. As, till then, the deliberations on long term O&M outsourcing were underway by the GENCO-III BoD, therefore the peculiar risks associated with the short term O&M services viz-a-viz long term O&M outsourcing were included in the proposal just to keep all the stakeholders on board regarding the shortcomings of the short term O&M services by the EPC contractor. The GENCO-V BoD also endorsed the same proposal along with its pros cons and risks.
The official said that majority procurement was made during the tenure of the previous regime while the present government was more involved in execution and assembling.
Outgoing ambassador pays farewell call on President Asif Ali Zardari at Aiwan-e-Sadr on Monday
Committee urges ministry to expedite appointment process, emphasizing improved governance
Former SCBA presidents say case will determine future course of country’s constitutional framework
Petitioner asks court to issue directives for registration of case against government officials
"Whether now or later, PTI will definitely demand its mandate," says Rana Sanaullah
PNAP leader condemns alleged manipulation and calls for fair and transparent elections in said constituency