Can BRT be completed in this century!: PHC judge seeks reply to questions on project
PESHAWAR: The Peshawar High Court (PHC) observed on Tuesday that whether the Pakistan Tehreek-e-Insaf (PTI) government would be able to complete the Bus Rapid Transit (BRT) project in this century.
“When will work on this project be completed? Work on 26 bus stations is going on and it could also take years,” Justice Muhammad Ibrahim Khan observed while hearing a writ petition in which the petitioner raised several questions over the long delay in completion and deficiencies in the project.
The petition was filed by Supreme Court lawyer Muhammad Isa about removal of deficiencies in the BRT project as citizens are facing hardships due to establishment of underpasses and overhead bridges at a distance of 1,600 meters.
To a question about completion of the project, the additional advocate general submitted that work on completion of 26 stations was going on. On this, Justice Ibrahim Khan observed that whether work on BRT would be completed in this century? The court once again directed the respondents to submit reply before October 16 – the date for next hearing in the case. At the previous hearing, the court had issued a notice to Khyber Pakhtunkhwa government through the secretary Transport and Mass Transit Department, project director for Project Management Unit, BRT Peshawar, and Provincial Departmental Working Party through its chairman.
The petitioner pointed out the deficiencies in the BRT project before the bench and stated that in Reach-III of the project at University Road, there are crossings at five places only, including Phase-III Chowk at Hayatabad, Gate No 2 at University of Peshawar, Town Chowk, Arbab Road and KFC Tehkal Payan, each at a distance of 1600 meters, which adds to congestion of the mixed traffic.
“There is no crossing for pedestrians at all. They will have to cover a distance of 1,600 meters to cross the road and the underpass at Jehangirabad has been closed for no reason. No drainage system has been provided at Reach-III. The service road has been merged with the main road,” the petitioner stated.
-
Meghan Markle, Prince Harry Likely To Attend Super Bowl Halftime Show 2026 -
AI Next Big Trial: Elon Musk Calls For ‘Galileo Test’ To Prove True Intelligence -
US Appeals Court Affirms Trump’s Immigration Detention Policy -
Bella Hadid, Adan Banuelos Rekindle Romance After Brief Separation -
Jay-Z Shares Bold Advice With Bad Bunny For NFL Super Bowl Halftime Show Appearance -
Epstein Probe: Bill, Hillary Clinton Call For Public Testimony Hearing -
Brooklyn Beckham Considers Adoption As Nicola Peltz Can't Carry A Baby -
Expert Discusses 'complications' Of Measles Outbreak -
Kaley Cuoco Recalls Her Divorce With Karl Cook: 'I Was Gonna Die' -
Celine Dion Reveals Music She's Listening To Lately -
HR Exec Kristin Cabot To Speak At Crisis PR Conference After Coldplay Incident -
Why Travis Kelce Says Taylor Swift Has Made Him 'so Much Better'? -
Halle Berry Credits This Hairstyle With Launching Her Acting Career -
Hailee Steinfeld Spills Her 'no-phone' Rule With Husband Josh Allen -
Bowen Yang Gets Honest About Post SNL Life: 'It’s An Adjustment' -
Charlize Theron Delivers Strong Message At 2026 Winter Olympics Opening Ceremony