KARACHI: The Sindh High Court (SHC) has set aside the Sindh energy department’s notification with regard to the grant of a permit to the Sindh Lakhra Coal Mining Company (SLCMC) for mining and exploration of coal in over 5,000 acres of land in Lakhra.
The high court directed the Sindh energy department to invite competitive bids and publicly announce them to grant any mining concession in the subject area with proven mining reserves.
The Pakistan Mineral Development Corporation (PMDC) had filed petitions with the SHC against refusal to renew its mining lease and the grant of mining permits to the SLCMC.
The petitioner submitted that its company was working under the administrative control of the federal ministry of petroleum and natural resources while the SLCMC was owned by the Sindh government. The petitioner’s counsel Zamir Ghumro submitted that the PMDC was granted mining lease for area of over 5,000 acres in Lakhra, district Jamshoro, in April 1984 for 30 years.
The SHC was informed that the petitioner had applied for the extension of the contract six months prior to the expiry of the contract in November 2014; however, the energy department rejected the applications for the extension of the mining leases. The counsel submitted that the petitioner’s appeals were pending before the competent authority but the energy department through the impugned notification granted the SLCMC the permit to work in over 5,000 acres of mining area in Lakhra on July 9, 2018, without waiting for the decision of the appeals.
The counsel submitted that coal mined by the petitioner was supplied to the Water and Power Development Authority (Wapda) on subsidised rates, which assisted the federal government in producing less-expensive electricity, and hence a renewal of the petitioner‘s mining-leases was in the public interest.
He submitted that the impugned decision of the appellate authority manifested that the refusal to renew the petitioner‘s mining leases was only for the reason that the petitioner was a federal government entity and the government of Sindh had already made up its mind to award a mining concession in the same area to the SLCMC, a company wholly owned by the government of Sindh. He submitted that the impugned notifications on July 9, 2018, granting mining permits to the SLCMC were issued by the caretaker provincial government which was contrary to its mandate under the Section 230 of the Elections Act, 2017.
Additional Advocate General Sindh Jawad Dero submitted that the petitioner did not have any vested right in the renewal of a mining lease as the energy department was the competent authority to refuse the renewal of a mining lease and to give preference to an entity registered in Sindh such as the SLCMC. He submitted that notwithstanding their respective control with the federal or provincial governments, both the petitioner and the SLCMC were private limited companies and therefore it was wrong on the petitioner’s part to portray the matter as a dispute between the federal government and the government of Sindh.
Reports indicate that they tried to breach one of gates, harassed staff, and even scaled walls of premises
Nasir praised role of Interior Minister Syed Mohsin Naqvi, who controlled situation with tolerance
A fierce exchange of fire ensued, but culprits managed to escape under cover of darkness
Police said booked leaders and BYC workers gathered at main Turbat Chowk
Experts say draconian internet censorship threatens to cut country off from promising future
Bokhari emphasised that cases have been registered against "Fasadis", and no one will be spared