Neelum-Jhelum power project: CoD of unit-4 to be attained in Dec
ISLAMABAD: The Commercial Operation Date (CoD) of Rs503 billion Neelum-Jhelum hydropower project will now complete in December this year, as the fourth unit of 242.25MW has been dismantled again.
The existing parts of the unit are being replaced and this process will be completed by mid of November. Chinese experts from Harbin city are installing new spare parts. The rotor of the unit got damaged at the very outset of making the project operational.
The unit-4 stopped functioning when the rubber ring of turbine got leaked. The unit-4 was then repaired and made operational, but the top management of the project refused to extend to the contractor the taking over certificate (ToC) unless genuine parts were replaced.
Chief Executive Officer of Neelum- Jhelum Hydropower Company Limited (NJHPCL) Brig (Retd) Mohammad Zareen said: “Yes, unit-4 has been dismantled and the required spare parts are being replaced by the Chinese team that came from Herbin city of China.
He said the process will take more than a week and after that the unit will start operating. He said the same unit 4 had already completed its reliability period. “And more importantly, the CoD of unity-4 will also be attained in December.”
The project, Mr Zareen said, has 4 units with each having the capacity to generate 242.25MW out of which the management has achieved the CoDs of three units. Once the CoD of the whole project is achieved, the government will withdraw the Neelum-Jhelum surcharge of Re0.10 per unit being charged from the end consumers in the electricity bills.
Mr Zareen said so far the project had generated 1.8 billion electricity units. To a question, he said 280 cumecs water is needed to run the four turbines to generate 969 MW of the project. The water flow has now dwindled in Neelum river to 90 cumecs and in the month of January the water flows will further go down to 36 cumecs. The water flows start improving from February and till April they will increase to 280 cumecs and from April to August, the project will be in a position to generate 969MW power for five months a year.
In the remaining months, water is stored in the dam and during peak demand hours the project generates the maximum electricity. The Executive Committee of National Economic Council (Ecnec) in 2002 approved the project at the cost of Rs84.502 billion.
-
Denzel Washington Surprises LeBron James -
Cillian Murphy's Hit Romantic Drama Exits Prime Video: Here's Why -
Paris Hilton Reveals What Keeps Her Going In Crazy Schedule -
Deep Freeze Returning To Northeastern United States This Weekend: 'Dangerous Conditions' -
Inside Dylan Efron's First 'awful' Date With Girlfriend Courtney King -
'Sugar' Season 2: Colin Farrell Explains What Lies Ahead After THAT Plot Twist -
‘Revolting’ Sarah Ferguson Crosses One Line That’s Sealed Her Fate As Well As Andrew Mountbatten-Windsor’s -
AI Rivalry Heats Up As Anthropic Targets OpenAI In Super Bowl Ad -
Kate Middleton, Prince William Share Message Ahead Of Major Clash -
Is Dark Matter Real? New Theory Proposes It Could Be Gravity Behaving Strangely -
Viral AI Caricature Trend: Is Your Personal Data Really Safe? -
Lil Jon’s Late Son, Nathan Smith Spoke Highly Of His Father Before His Tragic Death -
China Boosts Reusable Spacecraft Capabilities By Launching For The Fourth Time -
Bianca Censori On Achieving 'visibility Without Speech': 'I Don't Want To Brag' -
Skipping Breakfast? Here Are Some Reasons Why You Shouldn't -
'Concerned' Prince Harry Future Plans For Lilibet, Archie Exposed