Nine years on, Chakwal sewerage project not finished yetFrom Kh Babar SaleemCHAKWAL: People would have enjoyed the heavy rain that hit the Chakwal city the other day (Wednesday), if the things were normal as far as the civic amenities are concerned.But their reaction was exactly opposite as the downpour paralysed
By our correspondents
April 04, 2015
Nine years on, Chakwal sewerage project not finished yet
From Kh Babar Saleem
CHAKWAL: People would have enjoyed the heavy rain that hit the Chakwal city the other day (Wednesday), if the things were normal as far as the civic amenities are concerned.
But their reaction was exactly opposite as the downpour paralysed the routine, as rainwater accumulated on all major roads - Jhelum Road, Talagang Road and Pindi Road - and streets, turning the city into a lake that forced the people to stay indoors.
During Chaudhry Pervaiz Elahi’s tenure as chief minister, the Punjab government had approved sewerage system for Chakwal at the cost of more than Rs 300 million in 2006. The work on this project started briskly as the government wanted to attract voters in the 2007 elections.
By the time elections were held in Feb 2008 with an around two-month delay because of the assassination of Benazir Bhutto, all most 60 per cent project work had been completed, during which huge sewers were dug to drain rainwater and routine sewage for proper disposal.
But in 2008 elections, the PML-Q was defeated by PML-N lead by the Sharif brothers. The new PML-N government in Punjab stopped work on the project and launched an inquiry, claiming that million of rupees had been minted in the venture.
Since then seven years have passed but no Public Health Department official has been brought justice, while the construction still remains unfinished.
Many sewers were either dug or completely built as part of the planned sewerage system, but they have been encroached with the passage of time. The latest position is that these sewers are filled with garbage and the TMA has failed to ensure water flow in them. As such, even a normal rain converts the entire city into a lake, while rainwater enters into shops after heavy rains in monsoon season, with three to four feet of water accumulating in some areas.
The district administration’s failure to make this important sewerage and drainage project functional is causing great hardships to more than 0.2 million population of the city.
Citizens believe that every penny should be recovered from the corrupt officials but, at the same time, the project must be completed at the earliest so that they could get rid of this daily misery.
From Kh Babar Saleem
CHAKWAL: People would have enjoyed the heavy rain that hit the Chakwal city the other day (Wednesday), if the things were normal as far as the civic amenities are concerned.
But their reaction was exactly opposite as the downpour paralysed the routine, as rainwater accumulated on all major roads - Jhelum Road, Talagang Road and Pindi Road - and streets, turning the city into a lake that forced the people to stay indoors.
During Chaudhry Pervaiz Elahi’s tenure as chief minister, the Punjab government had approved sewerage system for Chakwal at the cost of more than Rs 300 million in 2006. The work on this project started briskly as the government wanted to attract voters in the 2007 elections.
By the time elections were held in Feb 2008 with an around two-month delay because of the assassination of Benazir Bhutto, all most 60 per cent project work had been completed, during which huge sewers were dug to drain rainwater and routine sewage for proper disposal.
But in 2008 elections, the PML-Q was defeated by PML-N lead by the Sharif brothers. The new PML-N government in Punjab stopped work on the project and launched an inquiry, claiming that million of rupees had been minted in the venture.
Since then seven years have passed but no Public Health Department official has been brought justice, while the construction still remains unfinished.
Many sewers were either dug or completely built as part of the planned sewerage system, but they have been encroached with the passage of time. The latest position is that these sewers are filled with garbage and the TMA has failed to ensure water flow in them. As such, even a normal rain converts the entire city into a lake, while rainwater enters into shops after heavy rains in monsoon season, with three to four feet of water accumulating in some areas.
The district administration’s failure to make this important sewerage and drainage project functional is causing great hardships to more than 0.2 million population of the city.
Citizens believe that every penny should be recovered from the corrupt officials but, at the same time, the project must be completed at the earliest so that they could get rid of this daily misery.
-
All You Need To Know Guide To Rosacea -
Princess Diana's Brother 'handed Over' Althorp House To Marion And Her Family -
Trump Mobile T1 Phone Resurfaces With New Specs, Higher Price -
Factory Explosion In North China Leaves Eight Dead -
Blac Chyna Opens Up About Her Kids: ‘Disturb Their Inner Child' -
Winter Olympics 2026: Milan Protestors Rally Against The Games As Environmentally, Economically ‘unsustainable’ -
How Long Is The Super Bowl? Average Game Time And Halftime Show Explained -
Natasha Bure Makes Stunning Confession About Her Marriage To Bradley Steven Perry -
ChatGPT Caricature Prompts Are Going Viral. Here’s List You Must Try -
James Pearce Jr. Arrested In Florida After Alleged Domestic Dispute, Falcons Respond -
Cavaliers Vs Kings: James Harden Shines Late In Cleveland Debut Win -
2026 Winter Olympics Snowboarding: Su Yiming Wins Bronze And Completes Medal Set -
Trump Hosts Honduran President Nasry Asfura At Mar-a-Lago To Discuss Trade, Security -
Cuba-Canada Travel Advisory Raises Concerns As Visitor Numbers Decline -
Anthropic Buys 'Super Bowl' Ads To Slam OpenAI’s ChatGPT Ad Strategy -
Prevent Cancer With These Simple Lifestyle Changes