Contracts signed for Dasu hydropower project

LAHORE: The Water and Power Development Authority (Wapda) on Monday signed two agreements, relocation of Karakoram Highway (KKH) and construction of the Right Bank Access Road, for the planned Dasu Hydropower Project.The Wapda spokesman termed it as a significant development for the implementation of the first stage of Dasu Hydropower

By our correspondents
March 17, 2015
LAHORE: The Water and Power Development Authority (Wapda) on Monday signed two agreements, relocation of Karakoram Highway (KKH) and construction of the Right Bank Access Road, for the planned Dasu Hydropower Project.
The Wapda spokesman termed it as a significant development for the implementation of the first stage of Dasu Hydropower Project with generation capacity of 2,160MW. He expressed the hope that the construction work on the project would start as soon as possible.
The contracts were signed between Wapda and China Civil Engineering Construction Company (CCECC) in a ceremony held at the Wapda House.
WAPDA Chairman Zafar Mahmood, Members of the Authority, CCECC Acting President Hao Xizhong, CCECC Assistant President Wang Xiangdong, and Dasu Project authorities were present on the occasion.
Dasu General Manager and Project Director Haji Muhammad Farooq and CCECC Director General Asia Oceanica Li Shiquan signed the contracts on behalf of their respective organisations.
The contract namely Dasu-KKH-01 worth Rs14.538 billion relates to the relocation of a 25-kilometer (Km) long stretch of the KKH. The contract is scheduled to be implemented in 546 days. The two-lane relocated stretch will be constructed at a higher attitude with the design standard prescribed for the KKH.
With the construction of this strip, the passage to the mechanical area and access to the dam site will be bypassed so as not to hinder the construction activities on the project. Most importantly, the people will also get hassle-free quality road service.
The second contract, namely Dasu-RAR-01, amounting to Rs2.713 billion, is scheduled to be implemented in one year. This 12-kilometer long road will be constructed on the right bank of the River Indus from Komila to Seo Dam site. At the moment, there is no proper road access except a jeep-track. The construction of the two-lane access road will not only enable the project authorities to initiate work on camps and proposed vocational training institutes, but also provide thousands of people of adjoining areas with all-weather quality road facility.
The district administration is currently busy in land acquisition for Stage-1 of Dasu Hydropower Project. The project authorities have, however, said that the process of acquiring land is slow, and expressed the apprehension that implementation on two contracts as well as the very completion of Stage-I of Dasu project will suffer a delay if the pace of land acquisition is not accelerated.
The project authorities said that taking notice of the slow pace of land acquisition, Federal Minister for Water and Power Khawja Muhammad Asif in a letter, requested the Khyber Pakhtunkhwa (KP) Chief Minister to speed up the land acquisition process. They said that the KP governor has also directed the district administration to accelerate the pace of acquiring land for the Dasu project.
It is important to mention here that the federal government is implementing the 4,320MW Dasu Hydropower Project in two stages. World Bank is financing Stage-I of the project with an IDA credit of $588.4 million and an IDA PCG of $460 million. Upon completion, the first stage will contribute more than 12 billion units of cheap, affordable, and environment-friendly electricity to the national grid. The project will not only add a sizeable quantum of low-cost electricity to the national grid but also provide relief to the consumers by reducing power tariff. To cap it all, the project will usher in a new era of socio-economic development in the far-flung areas of KP.