Rawalpindi : Rawalpindi Development Authority (RDA) and relevant authorities have reiterated their commitment to completing the Rawalpindi Ring Road within the revised time frame and budget while 37 per cent work on the project has been completed.
The road, once completed, is expected to significantly reduce traffic congestion and promote economic development in the region. According to a RDA official, the much-anticipated Ring Road project has seen 37 percent of its construction completed and the project would speed up after the approval of the revised PC-I.
The project was originally approved by Executive Committee of the National Economic Council (ECNEC) in December 2021 for Rs23.606 billion, with a completion period of 36 months. Later on, the project’s cost was updated to Rs26.969 billion on February 4, 2022. The project has seen its cost revised multiple times, now reaching Rs39 billion, as per the latest estimates.
The official informed that the RDA submitted the first revised PC-I of Rs44 billion and later re-submitted the document after the PDWP asked it to rationalize the cost. Subsequently, Rs32.9 billion PC-I was submitted in May, 2024.The revised PC-I of the instant project was cleared to be placed before CDWP/ECNEC for approval.
In this regard, the instant scheme was discussed in a pre-CDWP meeting in July 2024.The Pre-CDWP decided to extend the completion date to September 2025 due to the project’s complexity and to ensure quality.
It was also agreed that project escalation costs would be adjusted within the total revised cost by reducing the other overhead charges, ensuring the overall project cost remains unchanged.
Subsequently, in light of the meeting, Rs39bn PC-I was submitted with a gestation period of 46 months till September 2025.These revisions come as a result of inflation, rising material costs, and adjustments mandated by the Central Development Working Party (CDWP), which directed the inclusion of escalation charges in the revised project plan. The provision of price escalation had been made for the smooth execution and timely completion of the project.
RDA, which is overseeing the project, recently submitted a new Project Concept-1 (PC-1) with the revised cost to the Secretary of Housing. The proposal will now pass through the Punjab Planning and Development Wing (PDWP) and CDWP before being sent to the Executive Committee of ECNEC for final approval.
38.8 kilometres long Rawalpindi Ring Road, beginning at Banth Mor on GT Road and ending at the Thalian Interchange on the motorway. However, progress on the project has been slow, with only 37 per cent of the work completed so far.
Earthwork is 100 per cent complete. The initial completion deadline has now been extended to Sept 2025, reflecting the challenges the project has faced in its implementation. The original contract for the project was awarded to Frontier Works Organization (FWO) at a cost of Rs 26 billion.
However, due to inflationary pressures and increased material costs, the RDA was forced to revise the project’s cost, raising it initially to Rs44 billion. The PDWP later reduced this figure to Rs32.9 billion before it was sent for approval to the CDWP.
Subsequently, the CDWP instructed the RDA to prepare a further revised PC-1 incorporating updated cost escalation figures, which led to the current estimate of Rs39 billion. The Ring Road project has been in the pipeline for over three decades, facing delays and modifications under various governments.
Despite the progress, the pace of construction has remained behind schedule, with significant portions of the work still incomplete.
Currently, 63 per cent of the project’s construction remains to be done, and the contractor has been instructed to complete the remaining work by Sept, 2025. The Ring Road will have five interchanges at Baanth, Chak Baili Khan, Adiala Road, Chakri Road, and Thalian.
11 overpasses, bridges on 2 rivers, 6 canals and a railway bridge would be constructed under the project while 15 subways and 53 small bridges would also be constructed on the Rawalpindi Ring Road. A rest area would be constructed on the Ring Road. An industrial zone will also be established around the highway which will operate at a design speed of 120km/h with six lanes.
The construction work on the Banth and Chak Beli interchanges of the Ring Road has also started. The completion of the ring road would provide immense convenience to the citizens of Rawalpindi and Islamabad, the RDA spokesman said, adding that the project is of utmost importance for regional development as it will be a game changer for the people living in Rawalpindi and its suburbs.
Legendary poetess Parveen Shakir. — APP/FileIslamabad: The Parveen Shakir Trust will observe the 30th death...
Coordinator General of COMSTECH Prof Dr Muhammad Iqbal Choudhary seen in a meeting on the launch of the “COMSTECH...
Children seen at the 'Bookshaw' session for children and a health camp for mothers and babies organised by Association...
Fatima Jinnah Women’s University building can be seen. — ILM Website/FileRawalpindi: Fatima Jinnah Women...
A general view of the Margalla Hills Islamabad can be seen in this image. — Facebook/Islamabad Wildlife Management...
A picture from an exhibition based on rare pictures of Quaid-e-Azam inaugurated by Assistant Commissioner Murree on...