Islamabad:Capital Development Authority (CDA) is ramping up efforts to expedite the development of Islamabad’s sectors, as announced during a high-level meeting held on Monday.
Chaired by CDA Chairman Muhammad Ali Randhawa, the session brought together CDA Board Members and senior officials to address ongoing issues such as land acquisition and Built-Up Property (BUP) challenges.
Chairman Randhawa emphasized the need for coordinated efforts between the Engineering and Estate Wings to ensure the smooth execution of development projects. He also committed to personally visiting the sectors to monitor progress and push for faster resolution of obstacles.
In a progress report, the meeting revealed that 68% of development work in Sector C-14 is complete, with culvert construction underway. For Sector C-15, resolving possession issues was highlighted as a priority, while major works in Sector C-16 are almost finalized, with only a few streets left. In Sector E-12, the meeting was informed that 65% of the work in sub-sector E-12/1 is complete, with estimates being finalised for the remaining tasks.
Additional Foreign Secretary Ambassador Rizwan Saeed Sheikh. — Consulate General of Pakistan in Jeddah website/...
Participants seen at the Sarangi Season 7, an initiative under Serena Hotels’ Cultural Diplomacy.—...
The flags of Pakistan and Saudi Arabia. — Geo News/FileIslamabad: On Monday, Sardar Dr. Rashid Ilyas Khan, president...
Inspector General National Highways and Motorway Police Riffat Mukhtar Raja. — National Highway & Motorway Police...
Participants seen at a meeting of the Restaurants Caterers Sweets and Bakers Association.— RCSBA webstie/File...
Rawalpindi Cantonment Board building is seen in this undated picture. — APP/FileRawalpindi:To increase economic...